Victoria McLaughlin
New Zealand’s new digital court management system, Te Au Reka, represents one of the most significant changes to the courts in decades. It has been designed to support a more accessible, responsive and efficient court system.
We are preparing to introduce Te Au Reka into the Christchurch and Ashburton Family Court registries in late November. From March 2027, digital filing through the courts portal will become available to Family Court users in the South Island, with all Family Court locations expected to be using the new system by the end of May 2027.
Work is also progressing well on the next phase of Te Au Reka. Scoping for the criminal and civil jurisdictions has been completed and detailed design work is beginning. This is an important step toward extending the benefits of a modern digital platform across more of New Zealand’s courts.
LawNews’ September 30 article stated that the MoJ considered scrapping [the programme] in February 2025. This is incorrect.[please see Editor’s note *]
Large, multi-year public sector investments require careful planning, ongoing scrutiny and regular independent review. Te Au Reka is no different.
This includes the drawdown of funding as the programme moves into new phases. This is in line with the Treasury’s Better Business Case framework and requires the ministry to revisit all the options, including continuing as intended, changing direction or stopping.
This is a standard requirement and forms part of responsible programme management. Considering those options does not indicate an intention to cancel the programme. It demonstrates robust processes are being followed and that public investment decisions are being carefully tested.
As a significant government investment, the programme is also subject to comprehensive independent assurance. These reviews are designed to test assumptions, identify risks and provide confidence that delivery remains on the right track.
These activities continue to strengthen the programme as it progresses and have supported informed decisions at key points along the way.
As David Goddard KC, the judicial lead for Te Au Reka, has said: “The programme has encountered the normal challenges of any major multi-year IT project, but these challenges are being managed effectively and the programme is on track to deliver a much-needed digital transformation of New Zealand’s court system.”
The LawNews article also states that there have been budget blowouts. The programme’s cost profile has evolved over time, reflecting increased certainty as the programme progresses from procurement, through design and build. It is why contingency is part of the funding. Te Au Reka continues to operate within its financial approvals. [please see Editor’s note **]
Questions have been raised about why the full financial value has not been publicly released. Some commercial arrangements have been negotiated and agreed, while future phases and associated ongoing support arrangements remain subject to commercial discussions. In these circumstances, certain information remains commercially sensitive because releasing it could affect future negotiations and value-for-money outcomes.
Major government projects should be scrutinised. New Zealanders rightly expect transparency, accountability and strong stewardship of public investment.
Our focus remains on delivering a modern, secure and resilient digital court case management system that improves access to justice and supports more effective court services.
We are excited about continuing to work with the judiciary and the profession as we progress the design and build for the criminal and civil jurisdictions.
I’m confident that the delivery of Te Au Reka will result in a stronger foundation for trusted, responsive and future-ready courts.

Victoria McLaughlin is Deputy Secretary, Te Au Reka, at the Ministry of Justice
Editor’s notes:lawnews.nz/…10/DocumentPack_1_LawNews.pdf
* Te Au Reka is a customised digitisation programme being delivered by DXC Technology. The document Te Au Reka (Caseflow Management) Updated Implementation Business Case dated 24 March 2025, states on p22 that a workshop was conducted on February 4 that year to consider five options for the programme’s future. The fifth option was “Change to a Commercial Off-the-Shelf (COTS) solution and change provider”. In other words, sack DXC and scrap the work done so far in favour of adopting a ready-made solution from another supplier. Ditching the work done so far was not only considered, it was actually ranked second best of the five options, according to Table 4 p25.
** Te Au Reka is operating within its financial approvals, but those approvals needed to be increased by 15% in April 2025 because costs were higher than originally envisaged. Parliament’s Justice Select Committee said in its 2024-25 Annual Review of the Ministry of Justice: “We heard that the cost has increased by 15% since the detailed business case. The ministry attributed this to the product’s whole-of-life cost being much higher than expected when it went to market”. (p4). This was after McLaughlin told the select committee in September 2024 “we’re not looking at the moment for any new funding).

0 Comments