Neil Sands
Courts Minister Nicole McKee is confident this month’s reintroduction of the three strikes regime won’t overload the justice system, even though an ambitious digitisation program designed to make courts more efficient is not yet operating.
Officials told Parliament’s Justice Select Committee last week that the Te Au Reka project is “entirely on track” and set to launch in the Family Court next year before implementation was completed across the entire court system in late 2028.
The three strikes regime, which came into effect this month as part of the government’s law-and-order agenda, is expected to increase the courts’ workload with the imposition of progressively tougher sentences for repeat offenders.
McKee said she would have liked the court digitisation program – the Te Au Reka project – to have been in place for the change, but existing measures to improve timeliness in the courts would suffice until it was up and running.
“My understanding is that the courts do have a system that’s in place. It would have been ideal to use Te Au Reka but it hasn’t worked that way,” she said. “However, there is no issue with the way that the courts are set up with the three strikes regime, which came into place on June 17.”
Te Au Reka aims to replace the current paper-based system by digitising court documentation, including case management, making it more readily available across multiple jurisdictions.
Secretary of Justice Andrew Kibblewhite told the select committee that the project promised to be transformational.
“We think it will be the biggest change to have an impact on the courts, probably ever,” he said.
Kibblewhite said Te Au Reka, which means “the sweet flow” in te reo Māori, was set to meet its deadline for full implementation.
“Overall, the program is running to exactly the timeframes that we thought we had,” he said.
“The only adjustment is really that the phase one Family Court next year is probably initiating just a couple of months later, but it’ll finish in the same timeframes.
“And we’re front loading some of the work that was going to be in later phases into earlier phases, so the overall program is entirely on track. It’s going really well, and we’re getting really good engagement across the judiciary and with the profession.”
McKee said new courthouses in Whanganui and Papakura were due to be completed in 2027 and construction was underway on a court precinct in Tauranga.
She said the notoriously dilapidated courthouses at Waitākere and Rotorua were on the list for replacement, but not in the current budget cycle.
“Waitakere and Rotorua, we most definitely are still going to build,” she said. “We are just now looking at when we’re going to do it, and the appropriations for it. So that is not going to happen in this budget.”
Waitākere District Court is in such disrepair that staff are scared to turn the lights on when it rains for fear of electric shocks and people are being forced to use single-ply rolls in the toilet to prevent blockages.